Projects list Altay Pipeline SystemThe ‘Altay’ pipeline system is designed to provide for gas downstream from Russia to China and is an offshoot from the already existing major gas line that goes from Urengoy to Surgut to Chelyabinsk. At the design stage the project is currently in it is the compressor station in Purpe (Purpeyskaya CS), which has been admitted as the starting point for the pipeline. The station is part of the existing Urengoy-Surgut-Chelyabinsk gas trunk. The final Russian point of the pipeline is on top of Kanas pass in the mountains on the border with China. The total length of the Russian section of the pipeline system is 2,622 km. 2006-2007. Developing the Environmental Impact Assessment (EIA) as part of the Investment Feasibility Study of Altay project. The project facilities as per the current design include:
Ecocenter scope under the Environmental Impact Assessment task included:
The project has enjoyed a positive judgement on the part of the Federal Environmental Panel (State Environmental Expert Review – SEER). |